Boiler Replacement

  • At IVES and FES, the slabs are poured in the boiler rooms and all have passed inspections. The boilers themselves should be in within the next couple of weeks.  We are on schedule to have the new propane boilers at FES and IVES up and running by September 30.


    The outside work of tank placement at the other schools will begin very soon. They will begin digging the holes for the tanks at Check on September 4 and it will take about one week to finish. They will move to Willis after and then the high school. Once heating season is over, about the middle of April, they will get started on replacing those coal burners at Check, Willis, and the high school.